Information about Pert
The Program (or Project) Evaluation and Review Technique, commonly abbreviated PERT, is a model for project management designed to analyze and represent the tasks involved in completing a given project.
Overview
PERT is a method to analyze the tasks involved in completing a given project, especially the time needed to complete each task, and identifying the minimum time needed to complete the total project.This model was invented by Booz Allen Hamilton, Inc. under contract to the United States Department of Defense's US Navy Special Projects Office in 1958 as part of the Polaris mobile submarine-launched ballistic missile project. This project was a direct response to the Sputnik crisis. Some US government contracts required that PERT be used as part of management supervision.
PERT was developed in the 1950’s, primarily to simplify the planning and scheduling of large and complex projects. It was able to incorporate uncertainty by making it possible to schedule a project while not knowing precisely the details and durations of all the activities. It is more of an event-oriented technique rather than start- and completion-oriented, and is used more in R&D-type projects where time, rather than cost, is the major factor.
This project model was the first of its kind, a revival for scientific management, founded in Fordism and Taylorism. Though most companies now have their own project model, they all resemble PERT in some respect. Only DuPont corporation's critical path method was invented at roughly the same time as PERT.
The most recognizable feature of PERT is the "PERT Networks", a chart of interconnecting timelines. PERT is intended for very large-scale, one-time, complex, non-routine projects.
PERT terminology and conventions
Conventions
- A PERT chart is a tool that facilitates decision making; The first draft of a PERT chart will number its events sequentially in 10s (10, 20, 30, etc.) to allow the later insertion of additional events.
- Two consecutive events in a PERT chart are linked by activities, which are conventionally represented as arrows in the diagram above.
- The events are presented in a logical sequence and no activity can commence until its immediately preceding event is completed.
- The planner decides which milestones should be PERT events and also decides their “proper” sequence.
- A PERT chart may have multiple pages with many sub-tasks.
- PERT Charts are one of the tools used in the Earned Value Management Technique EVMT, used by many corporations today to track Earned Value.
Terminology
- A PERT event: is a point that marks the start or completion of one or more tasks. It consumes no time, and uses no resources. It marks the completion of one or more tasks, and is not “reached” until all of the activities leading to that event have been completed.
- A predecessor event: an event (or events) that immediately precedes some other event without any other events intervening. It may be the consequence of more than one activity.
- A successor event: an event (or events) that immediately follows some other event without any other events intervening. It may be the consequence of more than one activity.
- A PERT activity: is the actual performance of a task. It consumes time, it requires resources (such as labour, materials, space, machinery), and it can be understood as representing the time, effort, and resources required to move from one event to another. A PERT activity cannot be completed until the event preceding it has occurred.
- Optimistic time (O): the minimum possible time required to accomplish a task, assuming everything proceeds better than is normally expected
- Pessimistic time (P): the maximum possible time required to accomplish a task, assuming everything goes wrong (but excluding major catastrophes).
- Most likely time (M): the best estimate of the time required to accomplish a task, assuming everything proceeds as normal.
- Expected time (TE): the best estimate of the time required to accomplish a task, assuming everything proceeds as normal (the implication being that the expected time is the average time the task would require if the task were repeated on a number of occasions over an extended period of time).
- :: TE = (O + 4M + P) ÷ 6
- Critical Path: the longest possible continuous pathway taken from the initial event to the terminal event. It determines the total calendar time required for the project; and, therefore, any time delays along the critical path will delay the reaching of the terminal event by at least the same amount.
- Lead time: the time by which a predecessor event must be completed in order to allow sufficient time for the activities that must elapse before a specific PERT event is reached to be completed.
- Lag time: the earliest time by which a successor event can follow a specific PERT event.
- Slack: the slack of an event is a measure of the excess time and resources available in achieving this event. Positive slack(+) would indicate ahead of schedule; negative slack would indicate behind schedule; and zero slack would indicate on schedule.
Implementing PERT
The first step to scheduling the project is to determine the tasks that the project requires and the order in which they must be completed. The order may be easy to record for some tasks (e.g. When building a house, the land must be graded before the foundation can be laid) while difficult for others (There are two areas that need to be graded, but there are only enough bulldozers to do one). Additionally, the time estimates usually reflect the normal, non-rushed time. Many times, the time required to execute the task can be reduced for an additional cost or a reduction in the quality.In the following example there are seven tasks, labeled a through g. Some tasks can be done concurrently (a & b) while others cannot be done until their predecessor task is complete (c cannot begin until a is complete). Additionally, each task has three time estimates: the optimistic time estimate (a), the most likely or normal time estimate (m), and the pessimistic time estimate (b). The expected time (TE) is computed using the formula (a + 4m + b)/6.
| Activity | Predecessor | Opt. a | Norm. m | Pess. b | TE (a + 4m + b)/6 |
|---|---|---|---|---|---|
| a | -- | 2 | 4 | 6 | 4.00 |
| b | -- | 3 | 5 | 9 | 5.33 |
| c | a | 4 | 5 | 7 | 5.17 |
| d | a | 4 | 6 | 10 | 6.33 |
| e | b, c | 4 | 5 | 7 | 5.17 |
| f | d | 3 | 4 | 8 | 4.50 |
| g | e | 3 | 5 | 8 | 5.17 |
Note: All times listed are in work days (Mon - Fri, 8 A.M. to 5 P.M. with a one hour lunch break).
Once this step is complete, one can draw a Gantt chart or a network diagram (project management).

A Gantt chart created using Microsoft Project (MSP). Note (1) the critical path is in red, (2) the slack is the black lines connected to non-critical activities, (3) when using MSP, you must use the task ID when labeling predecessor activities, and (4) since Saturday and Sunday are not work days (as described above) some bars on the Gantt chart are longer if they cut through a weekend.
A network diagram can be created by hand or by using software such as Microsoft Project. There are two types of network diagrams, activity on arrow (AOA) and activity on node (AON). Activity on node diagrams are generally easier to create and interpret. To create an AON diagram, it is recommended (but not necessary) to start with a node named start. This "activity" has a duration of zero (0). Then you draw each activity that does not have a predecessor activity (a and b in this example) and connect them with an arrow. Next, since both c and d list a as a predecessor activity, their nodes are drawn with arrows coming from a. Activity e is listed with b and c as predecessor activities, so node e is drawn with arrows coming from both b and c, signifing that e cannot begin until both b and c have been completed. Activity f has d as a predecessor activity, so an arrow is drawn connecting the activities. Likewise, and arrow is drawn from e to g. Since there are no activities that come after f or g, it is recommended (but again not necessary) to connect them to a node labeled finish.

A network diagram created using Microsoft Project (MSP). Note the critical path is in red.
A node like this one (from Microsoft Visio) can be used to display the activity name, duration, ES, EF, LS, LF, and slack.
- The activity name
- The normal duration time
- The early start time (ES)
- The early finish time (EF)
- The late start time (LS)
- The late finish time (LF)
- The slack
In order to determine this information it is assumed that the activities and normal duration times are given. The first step is to determine the ES and EF. The ES is defined as the maximum EF of all predecessor activities, unless the activity in question is the first activity, which the ES is zero (0). The EF is the ES plus the task duration (EF = ES + duration).
- The ES for start is zero since it is the first activiy. Since the duration is zero, the EF is also zero. This EF is used as the ES for a and b.
- The ES for a is zero. The duration (4 work days) is added to the ES to get an EF of four. This EF is used as the ES for c and d.
- The ES for b is zero. The duration (5.33 work days) is added to the ES to get an EF of 5.33.
- The ES for c is four. The duration (5.17 work days) is added to the ES to get an EF of 9.17.
- The ES for d is four. The duration (6.33 work days) is added to the ES to get an EF of 10.33. This EF is used as the ES for f.
- The ES for e is the greatest EF of its predecessor activities (b and c). Since b has an EF of 5.33 and c has an EF of 9.17, the ES of e is 9.17. The duration (5.17 work days) is added to the ES to get an EF of 14.34. This EF is used as the ES for g.
- The ES for f is 10.33. The duration (4.5 work days) is added to the ES to get an EF of 14.83.
- The ES for g is 14.34. The duration (5.17 work days) is added to the ES to get an EF of 19.51.
- The ES for finish is the greatest EF of its predecessor activities (f and g). Since f has an EF of 14.83 and g has an EF of 19.51, the ES of finish is 19.51. Finish is a milestone (and therefore has a duration of zero), so the EF is also 19.51.
- The LF for finish is equal to the EF (19.51 work days) since it is the last activity in the project. Since the duration is zero, the LS is also 19.51 work days. This will be used as the LF for f and g.
- The LF for g is 19.51 work days. The duration (5.17 work days) is subtracted from the LF to get a LS of 14.34 work days. This will be used as the LF for e.
- The LF for f is 19.51 work days. The duration (4.5 work days) is subtracted from the LF to get a LS of 15.01 work days. This will be used as the LF for d.
- The LF for e is 14.34 work days. The duration (5.17 work days) is subtracted from the LF to get a LS of 9.17 work days. This will be used as the LF for b and c.
- The LF for d is 15.01 work days. The duration (6.33 work days) is subtracted from the LF to get a LS of 8.68 work days.
- The LF for c is 9.17 work days. The duration (5.17 work days) is subtracted from the LF to get a LS of 4 work days.
- The LF for b is 9.17 work days. The duration (5.33 work days) is subtracted from the LF to get a LS of 3.84 work days.
- The LF for a is the minimum LS of its successor activities. Since c has a LS of 4 work days and d has a LS of 8.68 work days, the LF for a is 4 work days. The duration (4 work days) is subtracted from the LF to get a LS of 0 work days.
- The LF for start is the minimum LS of its successor activities. Since a has a LS of 0 work days and b has a LS of 3.84 work days, the LS is 0 work days.
- The duration of path adf is 14.83 work days.
- The duration of path aceg is 19.51 work days.
- The duration of path beg is 15.67 work days.
Assuming these scenarios do not happen, the slack for each activity can now be determined.
- Start and finish are milestones and by definition have no duration, therefore they can have no slack (0 work days).
- The activities on the critical path by definition have a slack of zero; however, it is always a good idea to check the math anyway when drawing by hand.
- LFa - EFa = 4 - 4 = 0
- LFc - EFc = 9.17 - 9.17 = 0
- LFe - EFe = 14.34 - 14.34 = 0
- LFg - EFg = 19.51 - 19.51 = 0
- Activity b has a LF of 9.17 and a EF of 5.33, so the slack is 3.84 work days.
- Activity d has a LF of 15.01 and a EF of 10.33, so the slack is 4.68 work days.
- Activity f has a LF of 19.51 and a EF of 14.83, so the slack is 3.84 work days.

A completed network diagram created using Microsoft Visio. Note the critical path is in red.
See also
- Activity diagram
- Beta distribution
- Crash (schedule duration)
- Float (project management)
- Gantt chart
- Project network
- Project management
- Project planning
- Triangular distribution
External links
- Opensource software for making AON diagram
- The rudiments of PERT
- More explanation of PERT
- 3 Point Estimating Tutorial on VisionaryTools.com
- http://www.niwotridge.com/Resources/DomainLinks/EarnedValue.htm
Project management is the discipline of organizing and managing resources (e.g. people) in such a way that the project is completed within defined scope, quality, time and cost constraints.
..... Click the link for more information.
..... Click the link for more information.
project is a temporary endeavour undertaken to create a product or service[1].
..... Click the link for more information.
Origin
The word project comes from the Latin word projectum from projicere, "to throw something forwards" which in turn comes from pro-..... Click the link for more information.
project is a temporary endeavour undertaken to create a product or service[1].
..... Click the link for more information.
Origin
The word project comes from the Latin word projectum from projicere, "to throw something forwards" which in turn comes from pro-..... Click the link for more information.
Booz Allen Hamilton, Inc.
Private limited corporation
Founded 1914
Headquarters McLean, Virginia, USA
Key people Dr. Ralph Shrader, Chairman & CEO
Industry Management Consulting
Products Strategy Consulting
Technology Consulting
..... Click the link for more information.
Private limited corporation
Founded 1914
Headquarters McLean, Virginia, USA
Key people Dr. Ralph Shrader, Chairman & CEO
Industry Management Consulting
Products Strategy Consulting
Technology Consulting
..... Click the link for more information.
- Department of Defense redirects here. For the defense departments in governments of other countries, see defence ministry.
United States
Department of Defense
..... Click the link for more information.
19th century - 20th century - 21st century
1920s 1930s 1940s - 1950s - 1960s 1970s 1980s
1955 1956 1957 - 1958 - 1959 1960 1961
Year 1958 (MCMLVIII
..... Click the link for more information.
1920s 1930s 1940s - 1950s - 1960s 1970s 1980s
1955 1956 1957 - 1958 - 1959 1960 1961
Year 1958 (MCMLVIII
..... Click the link for more information.
The Polaris missile was a submarine-launched, two-stage solid-fuel nuclear-armed ballistic missile (SLBM) built during the Cold War by Lockheed for the United States Navy.
..... Click the link for more information.
..... Click the link for more information.
submarine is a watercraft that can operate underwater. Military submarines were first widely used in World War I and are used by all major navies today. Civilian submarines and submersibles are used for scientific work at depths too great for human divers.
..... Click the link for more information.
..... Click the link for more information.
The 'Sputnik crisis' was a turning point of the Cold War that began on October 4, 1957 when the Soviet Union launched the Sputnik 1 satellite. The USA had believed itself to be the world leader in space technology and thus the leader in missile development.
..... Click the link for more information.
..... Click the link for more information.
Fordism, named after Henry Ford, has different meanings in the United States and Europe.
..... Click the link for more information.
Fordism in U.S.
In the U.S. Fordism is the economic philosophy that widespread prosperity and high corporate profits can be achieved by high wages that allow the workers to purchase..... Click the link for more information.
Scientific management, also called Taylorism or the Classical Perspective, is a method in management theory that determines changes to improve labour productivity. The idea was first coined by Frederick Winslow Taylor in The Principles of Scientific Management.
..... Click the link for more information.
..... Click the link for more information.
Dupont, DuPont, Du Pont, or du Pont may refer to:
..... Click the link for more information.
Companies
- E.I. du Pont de Nemours and Company (DuPont), the world's fourth largest chemical company
- Du Pont Motors
..... Click the link for more information.
The Critical Path Method, abbreviated CPM, or critical path analysis, is a mathematically based algorithm for scheduling a set of project activities. It is a very important tool for effective project management.
..... Click the link for more information.
..... Click the link for more information.
..... Click the link for more information.
Gantt chart is a popular type of bar chart that illustrates a project schedule. Gantt charts illustrate the start and finish dates of the terminal elements and summary elements of a project. Terminal elements and summary elements comprise the work breakdown structure of the project.
..... Click the link for more information.
..... Click the link for more information.
Program (or Project) Evaluation and Review Technique, commonly abbreviated PERT, is a model for project management designed to analyze and represent the tasks involved in completing a given project.
..... Click the link for more information.
..... Click the link for more information.
Microsoft Project (or MSP) is a project management software program developed and sold by Microsoft which is designed to assist project managers in developing plans, assigning resources to tasks, tracking progress, managing budgets and analyzing workloads.
..... Click the link for more information.
..... Click the link for more information.
Float (a.k.a Slack) in project management is the amount of time that a terminal element in a project network can be delayed by, without causing a delay to:
..... Click the link for more information.
- subsequent terminal elements (free float)
- project completion date (total float).
..... Click the link for more information.
Theory of Constraints (TOC) is an overall management philosophy that aims to continually achieve more of the goal of a system. If that system is a for-profit business, then the goal is to make more money, both now and in future.
..... Click the link for more information.
..... Click the link for more information.
Float (a.k.a Slack) in project management is the amount of time that a terminal element in a project network can be delayed by, without causing a delay to:
..... Click the link for more information.
- subsequent terminal elements (free float)
- project completion date (total float).
..... Click the link for more information.
The Critical Path Method, abbreviated CPM, or critical path analysis, is a mathematically based algorithm for scheduling a set of project activities. It is a very important tool for effective project management.
..... Click the link for more information.
..... Click the link for more information.
Float (a.k.a Slack) in project management is the amount of time that a terminal element in a project network can be delayed by, without causing a delay to:
..... Click the link for more information.
- subsequent terminal elements (free float)
- project completion date (total float).
..... Click the link for more information.
..... Click the link for more information.
In the Unified Modeling Language, an activity diagram represents the business and operational step-by-step workflows of components in a system. An activity diagram shows the overall flow of control.
..... Click the link for more information.
..... Click the link for more information.
beta distribution is a family of continuous probability distributions defined on the interval [0, 1] parameterized by two non-negative shape parameters, typically denoted by α and β.
..... Click the link for more information.
..... Click the link for more information.
..... Click the link for more information.
Float (a.k.a Slack) in project management is the amount of time that a terminal element in a project network can be delayed by, without causing a delay to:
..... Click the link for more information.
- subsequent terminal elements (free float)
- project completion date (total float).
..... Click the link for more information.
Gantt chart is a popular type of bar chart that illustrates a project schedule. Gantt charts illustrate the start and finish dates of the terminal elements and summary elements of a project. Terminal elements and summary elements comprise the work breakdown structure of the project.
..... Click the link for more information.
..... Click the link for more information.
A project network is a graph (flow chart) depicting the sequence in which a project's terminal elements are to be completed by showing terminal elements and their dependencies.
The work breakdown structure or the product breakdown structure show the "part-whole" relations.
..... Click the link for more information.
The work breakdown structure or the product breakdown structure show the "part-whole" relations.
..... Click the link for more information.
Project management is the discipline of organizing and managing resources (e.g. people) in such a way that the project is completed within defined scope, quality, time and cost constraints.
..... Click the link for more information.
..... Click the link for more information.
This article is copied from an article on Wikipedia.org - the free encyclopedia created and edited by online user community. The text was not checked or edited by anyone on our staff. Although the vast majority of the wikipedia encyclopedia articles provide accurate and timely information please do not assume the accuracy of any particular article. This article is distributed under the terms of GNU Free Documentation License.
Herod_Archelaus
